TO ALL LEASEHOLDERS AND RESIDENTS

PLEASE BE AWARE OF THE VARIOUS WORKS BEING CARRIED OUT IN THE COMMUNAL HALLWAYS AND LANDINGS OVER THE NEXT 3-6 MONTHS, WHICH START ON MONDAY 12 FEBRUARY AND WILL INCLUDE THE FOLLOWING:

ADDITIONAL FIRE STOPPING IN ALL COMMUNAL HALLWAYS- the works will include

  • Protective carpet covering and holes cut in ceiling above all flat front doors in preparation
  • Fire stopping installed above all flat front doors and communal riser cupboards
  • Fire stopping around lift doors
  • Intumescent strips/drop down seals to all communal riser cupboard doors & fire doors
  • Inspection hatches installed above front doors, making good and clearing up
  • Each landing/hallway may take a couple of weeks depending on location
  • Work will start in Admiralty Tower (preparation has already started), then Gloucester, Brunswick and Marlborough Houses before progressing through Queen Anne to Richmond House (including the smaller blocks underneath) and then the Cross Street blocks

EXTERNAL MASONRY REPAIRS AROUND PODIUM GARDEN

  • Scheduled to start around Spring when the fire stopping has been finished
  • The relevant work areas will be cordoned off with H&S measures in place
  • We will be in contact with those properties affected nearer the time

EXTERNAL CAPPING REPAIRS/SEALING IN IDENTIFIED AREAS

  • Scheduled to start around early Spring
  • We will be in contact with those properties affected by damp ingression to arrange access nearer the time

If you have any questions, please contact the Concierge desk on 07825 600121 concierge@aqportsmouth.co.uk or managing agents on manager@aqportsmouth.co.uk

Thank you

08 February 2018

 

Thank you

 

08 February 2018